Poletti Power Plant De-Construction
NY Power Authority Works To Safely Remove Materials
The bottom line is that current plans call for the de-construction of the old Poletti Power plan to be completed by December 31, 2014. Current planning is underway to figure out how to approach the removal of the old plant materials. Some of the issues include routing of them via trucks through Astoria or via barge on the East River.
We were told that the plant is not being demolished, but rather de-constructed in a manner similar to reverse construction. The New York Power Authority, a government agency, is managing the project.
Click here for the rest of our report, including photos of the NY Power Authority & Poletti Power Plant de-construction.
Poletti Power Plant De-Construction
NY Power Authority Works To Safely Remove Materials
New York - NY Power Authority
Edward Birdie, Director of the SENY Community Affairs Public, Government & Regulatory Affairs, was joined by Andrea Luongo, Project Manager of the Poletti Plant site de-construction. Andrea spent a little time orienting us to the landscape of ‘The Site’ which is a large energy complex in northwest Astoria and Queens, that represents the significant portion of the Queens County power complex which is home to 60% of NYC’s power supply.
Andrea gave us some background on the New York Power Authority. The NYPA is the largest state run power company in the U.S. with 16 power generation sites and 1400 miles of transmission lines. They provide 20% of NY State’s power and 70% of it is generated by renewable means [hydropower]. They are a leader in renewable energy technologies, energy efficiency and electric transportation. And the NYPA has funded over $1 billion in clean power initiatives, resulting in savings of 1.6 million barrels of oil per annum and 262,000 tons of green house gasses.
History of the Poletti Power Plant in Astoria Queens
The power plant began power generation in 1977. In 1980 the power plant was outfitted to enable it to generate electricity using natural gas, thus making it a dual-fuel plant. In 1982 the power plant was named after former NYS Governor and NYPA Trustee, Charles Poletti.
New Power Plants in Queens & Deconstruction of Poletti Power Plant
In 1998 it was decided to replace the power plant with a new, state-of-the-art, 500 megawatt combined cycle power plant. And in 2002 the NY Power Authority signed a Stipulation Agreement, with more than six government and local civic groups like the
The Poletti Power Plant de-commissioning encompasses three separate projects: 1) the de-mineralized water plant, 2) the fuel oil yard and 3) the Unit #6 power plant. These projects were to take place over a five-year period from 2010 – 2014. The first two projects have been completed and planning for the third is underway and scheduled for completion by December 31, 2014.
Poletti Power Plant Timeline - United Community Civic Association
Currently there are a number of activities in progress. These include securing insurance certificates and bonding of those involved in the project. And the creation of a comprehensive logistics plan and site specific health and safety plan [HASP]. They are also working to find the best access / egress routes through which the deconstructed materials will move. And they are marking off the staging areas within which the work will take place to ensure that everything goes smoothly.
NY Power Authority - Sustainable & Regenerative
Andrea noted that the deconstruction project has a price tag of $30 million, but that by salvaging equipment and materials from the old Poletti Power Plant and selling them at market; the NY Power Authority was able to recoup $9 million of the deconstruction costs.
United Community Civic Association - Community Concerns & Questions
The United Community and Civic Association group’s questions were quite good. Someone asked about how much asbestos was on the site. Andrea noted that the Poletti Power Plant had been well managed and that asbestos mitigation had been done throughout its 40 year life, so that the primary asbestos deposits were limited to the boiler, gaskets and roof, with some in an adjacent building.
Andrea and Edward noted that in 2010 and 2011 they had quietly removed the de-mineralized water plant materials through the neighborhood without a complaint. They also said the contractor would be required to move the materials in compliance with state and federal regulations to ensure safety.
Someone asked about the size and future of the site. We were told that at this time there aren’t any plans for it, and that they would get back to us on the size of the vacated site.
At the end of the question and answer session there was pretty enthusiastic applause. I took it as a sign that the folks in the room seemed generally pleased with how things were being managed and communicated.
Thanks - United Community Civic Association & New York Power Authority
We want to thank the Rose Marie Poveromo and the United Community Civic Association for hosting this presentation, as well as Edward Birdie and Andrea Luongo and the New York Power Authority for providing an informative session.
Astoria Neighborhood Links
Click on these advertisements for promotions, discounts and coupons by retailers and restaurateurs in Astoria and nearby Queens.
Click this link to go to the:
Astoria Neighborhood or Astoria Business Directory
Astoria Real Estate or Events & Things To Do In Astoria
Restaurants In Astoria or Astoria Shops & Shopping
Site Search Tips. 1) For best results, when typing in more than one word, use quotation marks - eg "Astoria Park". 2) Also try either singular or plural words when searching for a specific item such as "gym" or "gyms".
$element(bwcore,insert_search,N)$
Click this link to search for something in our Queens Business Directory.
$element(adman,groupad,Sectional2 Ad)$
Click the log in link below to create an ID and post an opinion.
Or send this story to a friend by filling in the appropriate box below.